SHD Composites LTC210
- Chemical Family
- Epoxy & Epoxy Derivatives
Shanghai Sunwise Chemical LTC210 Prepreg is designed to cure at low temperatures whilst giving the potential for high temperature tooling. Typical initial cure cycles are 24 hrs at 45°C or 10 hrs at 55°C, followed by a 200°C post cure. LTC210 can be supplied on a variety of fabrics to meet your cost and manufacturing requirements.
Product families
Applications
- Consumer Goods — Sports & Recreation
- Tooling & Moldmaking
Product Families
- Thermoset Prepregs
Other characteristics
- Functions
- Prepreg
- Polymer Name
- Epoxy Resins & Compounds
- Processing Methods
- Prepreg Processing
- Reinforcement Material
- Carbon Fibers, Glass Fibers
- Carbon Fibers
- Glass Fibers
- Markets
- Consumer Goods
- Industrial
- Key Features
Cure temperature from 45°C to 70°C; Service temperature up to 200°C after post cure; Low CTE and shrinkage; Work life at 20°C: 4 days; Storage life at -18°C: 12 months; Very low VOC content – no added solvents during manufacture; Excellent handleability in warmer conditions
- Technology
- Composite Materials
- Packaging Type
- Bags
- Labeling Claims
- Low VOC
- Health and Safety
This material contains epoxy resin which can cause allergic reactions with skin contact and must avoid repeated and prolonged skin contact.; The following precautions must be taken when using epoxy resin prepregs:; Overalls must be worn.; Impervious gloves must be worn.; Curing schedule is meant to be as a guide only and is subject to local conditions.; To avoid exotherm, particular care must be taken with thick laminates.; Ramp rates must not exceed 1.0°C/min during initial cure and 0.3°C/min during post cure.
- Material Features
- Ease of Handling
- Low Shrinkage
- Temperature Resistance
- Storage and Out Life
This material should be kept frozen at -18°C. It must be kept sealed in a polythene bag which must not be opened until fully thawed to room temperature. If the material is not fully used, then the material must be resealed in the polythene bag to prevent moisture absorption.
- Typical Applications
- Low CTE tooling
- Recommended Cure Cycle
*The initial cure duration will depend on part and tool geometry, volume, mass, etc.#; Curing Schedule is meant to be a guide only and is subject to local conditions.; To avoid exotherm particular care must be taken with thick laminates.; Ramp rates must not exceed 1.0°C per minute during initial cure.; Ramp rates must not exceed 0.3°C per minute during post cure (free standing).
- Composite Materials Functions
- Prepreg
- Composites Processing Methods
- Prepreg Processing
Technical data
Table 1 of 1
6 rows| Characteristic | Value | Unit | Method |
|---|---|---|---|
| Cure Temperature | 45 - 70 | °C | — |
| Cure Time | 40 - 4 | — | hrs,mins |
| Outlife | 4 | — | months |
| Tg Onset | 202 | — | — |
| Tg Peak | 221 | — | — |
| Service Temperature | 200 | °C | — |